New Home Construction
Moving Inside to Finish Up
May 29, 2024 working inside. The pocket doors have been installed and the guys are working on interior doors and trim.
Series of Framing Pictures Starting November, 20 2023
This is the first day of framing. Sergio, the guy who is managing the job, estimates this part of the house build will take about three weeks. We have heard that this is the most
Series of Foundation Progress Pictures Starting October 14, 2023
This post will be a series of pictures on the progress of the foundation work starting on October 14, 2023.
Series of Dirt Work Pictures Starting August 4, 2023
This post will be a series of pictures on the progress of the dirt work for the foundation starting 8-4-2023. Check
Power Meter Loop Ready To Go
As of today, August 21, the power company meter loop is ready to go. All approvals, inspections and easements have
These Are The People Who Built Our Home
From left to right this is Anthony and William. These are the guys that worked for 2 days in 105+ degree heat to complete
Beginning of Dirt Work for the Foundation August 1, 2023
Construction has started. The first piece of equipment was delivered 8-1-2023 and
New Home Orientation and Placement July 24, 2023
On Monday, July 24 2023, the decision was made on where to place and how to orientate the home for the view that